College Avenue Belfast

College Avenue, Belfast | June 2016 – June 2018

Development Details Planning Permission obtained for 120,000 sq ft offices, 250 bed hotel and 147 car parking spaces. High profile location within Belfast City Centre.

The student development is comprised of welfare facilities, associated ancillary accommodation, external areas to include landscaped courtyards and an enclosed car park.

Contact Details

Please do not hesitate to contact us should you wish to discuss any matters relating to the site:

Project Manager: Ciaran Tiffney
Email: ciaran.tiffney@mcaleer-rushe.co.uk

Site Manager: Jonathan Murphy
Email: jonathan.murphy@mcaleer-rushe.co.uk

Alternatively you can contact our head office on 028 8676 3741


Framing works have been completed

Framing works have been completed to level 10 and is currently progressing on level 11. Fit out works have commenced on the 1st – 6th Floors. The brickwork, windows and curtain walling are currently progressing on the external façade with stone commencing next week.

College-Avenue-Newsletter-September-2017.pdf

29th August 2017

Framing works have been completed

Framing works have been completed to level 9 and are currently progressing on level 10. Fit out works have commenced on the 1st – 5th Floors. External façade is progressing with windows being installed and brickwork commencing.

College-Avenue-Newsletter-August-2017.pdf

29th July 2017

Erection of scaffold progressing

The main scaffold surrounding the building is progressing and will follow the structure floor by floor. Protective fans are installed on College Ave and College Street to protect the public as the building rises. Partitions forming rooms and services installations have commenced on level 1 and 2.

College-Avenue-Newsletter-May-2017.pdf

29th May 2017

Erection of scaffold has commenced

Erection of scaffold has commenced. This will progress on to College Court by April and continue on to College Street and College Ave thereafter.

College-Avenue-Newsletter-Mar-2017.pdf

29th March 2017

Structure continues floor by floor

The structure will continue floor by floor. The first section of level 3 will be poured next week and we will continue with approx. 1 large weekly floor slab pour and daily pours off walls and columns.

College-Avenue-Newsletter-Feb-2017.pdf

24th February 2017

First Floor slab

College Avenue #Belfast starting to take shape, first floor slab pour almost complete.

College Avenue Newsletter Jan 2017.pdf

12th January 2017

Concrete Pour

Nothing #concrete but we’re almost there with todays pour in College Avenue #Belfast

College Avenue Newsletter Dec 2016

15th December 2016

Piling work completed

All piling works have been completed with all drainage currently just completed.
Formwork sub-contractor on site in past week and commencing their works by jumping the lift shaft.

1st November 2016

Site drainage started – Piling complete

Pile caps being excavated, piles broke down and pile caps cast ongoing. Site drainage started – Piling complete

10th October 2016

Excavation of pile caps

Piles on going, Started excavation of pile caps and breaking down piles Tower cranes installed

15th September 2016

Piling Ongoing

Piling Ongoing

6th August 2016

Piling Continues

1st week of Piling complete

IMG_1532

31st July 2016